The Cost Performance Index (CPI) is a project management metric used to measure the efficiency of cost performance on a project.
It is calculated by dividing the earned value (EV) by the actual cost (AC).
The Cost Performance Index (CPI) includes two key components: the earned value (EV) and the actual cost (AC).
Earned Value (EV) |
The earned value represents the budgeted cost of work performed. It is the value of the work completed based on the project's planned budget. Earned value is typically determined by measuring the progress and completion of specific project tasks or deliverables. It provides an objective measurement of the work accomplished, regardless of the actual cost incurred. Ex: The construction project involves building a house, and the planned budget for completing the foundation work is $50,000. After completing the foundation work, the project manager assesses the progress and determines that the earned value is $40,000, indicating that 80% of the planned work has been completed. |
Actual Cost (AC) |
The actual cost is the total cost incurred for the work performed up to a specific point in time. It includes all the expenses related to the project, such as labor costs, material costs, equipment costs, subcontractor costs, and any other direct or indirect costs associated with the project. The actual cost reflects the real expenses incurred during the project execution. Ex: The project manager reviews the project expenses related to the foundation work and finds that the actual cost incurred is $55,000. It includes expenses for labor, materials, equipment, subcontractors, and other direct or indirect costs associated with the foundation work. |
By comparing the earned value (EV) with the actual cost (AC), the Cost Performance Index (CPI) indicates the cost efficiency of the project.
It quantifies whether the project is performing better or worse than planned in terms of cost.
The formula to calculate the Cost Performance Index (CPI) is:
CPI = EV / AC
A CPI value greater than 1 indicates that the project is performing better than planned, while a CPI value less than 1 suggests that the project is performing worse than planned in terms of cost efficiency.
Based on this example, we have the following values:
Using these values, we can calculate the Cost Performance Index (CPI) as follows:
CPI = EV / AC = $40,000 / $55,000 = 0.727
The CPI value of 0.727 suggests that the project's cost performance is worse than planned, as the actual cost (AC) exceeds the earned value (EV).
The project has incurred higher costs than expected relative to the completed work.
It indicates a potential cost overrun that requires attention and corrective action to bring the cost performance back on track.
Cost Monitoring |
The CPI allows project managers to monitor and assess the cost performance of a project. By comparing the earned value (EV) with the actual cost (AC), the CPI provides a quantitative measure of how efficiently the project is utilizing its resources. It helps identify cost overruns or cost savings, enabling proactive measures to be taken to address any budgetary issues. |
Performance Evaluation |
The CPI helps evaluate the overall performance of a project in terms of cost efficiency. A CPI value greater than 1 indicates that the project is performing better than planned, while a CPI value less than 1 suggests that the project is not meeting cost expectations. By tracking the CPI over time, project managers can identify trends, assess the impact of changes, and make informed decisions regarding budgeting, resource allocation, and project adjustments. |
Decision Making |
The CPI provides objective data that can guide decision-making processes related to project management. It enables project managers to determine if adjustments need to be made in terms of cost control, resource allocation, scheduling, or scope management. The CPI helps prioritize areas that require attention and guides decision-making toward optimizing cost performance. |
Early Warning System |
The CPI serves as an early warning system, alerting project managers to potential cost-related issues. If the CPI value is consistently below 1, it indicates that the project is experiencing cost overruns and may require immediate corrective actions. By identifying such issues early on, project managers can mitigate risks, take corrective measures, and prevent further cost deviations. |
Benchmarking and Improvement |
The CPI can be used for benchmarking and performance improvement purposes. Project managers can compare the CPI of their current project with past projects or industry standards to identify areas for improvement. It helps in setting realistic cost targets for future projects, improving cost estimation accuracy, and enhancing overall project performance. |
To use the Cost Performance Index (CPI) effectively in project management, follow these steps:
1 |
Define Baseline and Measurement Points |
Establish a baseline for the project's planned cost and schedule, usually in the form of a budgeted cost baseline. Identify specific measurement points or time intervals at which you will assess the project's actual cost and progress. |
2 |
Calculate Earned Value (EV) |
Determine the earned value (EV) by assessing the progress and completion of work against the planned schedule. It involves quantifying the value of work completed for each task, work package, or phase of the project. Use a predetermined method such as the percentage of completion, milestone achievement, or physical units of measurement. Sum up the earned values to obtain the total earned value for the project up to the measurement point. |
3 |
Track Actual Cost (AC) |
Record and track the actual costs incurred for the project up to the measurement point. It includes all expenses related to labor, materials, equipment, subcontractors, overheads, and any other direct or indirect costs. Ensure accurate and up-to-date tracking of costs to reflect the actual financial expenditure. |
4 |
Calculate (CPI) |
Use the formula CPI = EV / AC to calculate the CPI. Divide the earned value (EV) by the actual cost (AC) to obtain the CPI value. |
5 |
Interpret the CPI Value |
Analyze the CPI value to assess the project's cost performance. A CPI greater than 1 indicates that the project is performing better than planned in terms of cost efficiency, while a CPI less than 1 suggests underperformance. The magnitude of the deviation from 1 provides additional insights into the extent of the cost performance deviation. |
6 |
Assess Performance Trends |
Monitor the CPI over time to identify trends and patterns in cost performance. Analyze how the CPI values change at different measurement points or intervals. It helps to identify if the project's cost performance is improving, deteriorating, or remaining consistent. Trends can provide early indicators of potential cost issues and guide corrective actions. |
7 | Analyze Variances |
Compare the CPI with the planned budget and other project performance metrics to understand the reasons for cost deviations. Analyze the variances between the planned cost, earned value, and actual cost to identify the specific areas where costs are exceeding or falling short of expectations. This analysis helps identify the root causes of cost performance deviations. |
8 |
Take Corrective Actions |
Based on the CPI analysis and variance identification, develop and implement appropriate corrective actions. Adjust the project budget, revise the schedule, optimize resource allocation, or implement cost control measures to address cost overruns or improve cost performance. Monitor the impact of corrective actions on the CPI and make further adjustments as needed. |
9 |
Communicate and Report |
Share the CPI results, analysis, and corrective actions with relevant stakeholders, such as the project team, management, and clients. Provide regular updates on the project's cost performance, highlighting any significant changes, trends, or mitigation measures. Effective communication ensures transparency, collaboration, and alignment among stakeholders. |
10 |
Continuously Monitor and Update |
Regularly track the CPI, reassess the budgeted cost baseline, and adjust the measurement points as the project progresses. Monitor the effectiveness of corrective actions and refine them as necessary. Keep stakeholders informed about any changes in the CPI and its implications for the project's cost performance. |