Question 1 - ID: 931382
Once a project’s business case has been approved, what should be done next?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Once a project’s business case is approved, the project can be initiated. The develop project charter process launches the project.
Question 2 - ID: 211005
During the development of the project stakeholder engagement plan, the project manager is usually dependent on the expert judgment of senior stakeholders to identify and plan effective stakeholder management strategies. Which of the following stakeholders cannot guide the project manager in developing effective strategies for internal stakeholders?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Only internal stakeholders can provide expert judgment on effective management strategies for internal stakeholders. Project customers are important stakeholders but usually they lack the knowledge on internal stakeholders, and hence cannot provide accurate feedback.
Question 3 - ID: 111849
Nancy’s project has a large number of key positive and negative stakeholders. To ensure the project’s success, it is essential to manage the influential negative stakeholders closely. Do the key positive stakeholders need to be managed, too?
Select one
 
A.
B.
C.
D.
Answer and explanation:
It is just as important to manage the positive stakeholders as it is to manage the negative stakeholders. Stakeholders' expectations and interests change over time. In order to ensure the success of the project, the positive stakeholders should be managed closely to retain their support and commitment to the project.
Question 4 - ID: 581090
Henry is the project manager for a process improvement project. Henry is a recently hired Six Sigma expert. David is the process owner of the process Henry must optimize. During the project kick-start meeting with the project sponsor, David said he supports all continuous improvement efforts. However, David is unaware of the Six Sigma technique and feels threatened by the newly hired expert, and as a result, is blocking Henry’s ideas. What is David’s current engagement level with the project?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Although david claims that he is supportive of all improvement initiatives, his behavior is not coherent with his claim. Since david is blocking henry’s idea, he is in effect, resistant of the project.
Question 5 - ID: 791745
An important aspect of project management is the handling of stakeholder expectations. Typically, at what level are the stakeholders with respect to the project manager?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Project stakeholders are persons and organizations having a stake in the project. They typically exist at different levels and have varying degrees of authority. For example, the project sponsor will be at a higher level and have greater authority than the project manager. In contrast, a team member may be at a lower level and have lesser authority.
Question 6 - ID: 451645
Organizational process assets are key inputs to the Manage Stakeholder Engagement process. The key elements of the organizational process assets that are used during this process are organizational communication requirements, issue management procedures, and the change control procedures. Which of the following is also a key organizational process asset that must be considered during this process?
Select one
 
A.
B.
C.
D.
Answer and explanation:
All of the given choices are organizational process assets. However, the organizational policies and templates are more relevant during the planning phase of the project. For the manage stakeholder engagement process, a process from the executing process group, historical information about previous projects is considered a critical input from the organizational process assets.
Question 7 - ID: 431156
Adam has just taken over a construction project. The project is currently in the planning phase of the project lifecycle. Adam’s next deliverable is to produce an effective stakeholder engagement strategy. Which of the following is the most important component of an effective stakeholder engagement plan?
Select one
 
A.
B.
C.
D.
Answer and explanation:
An effective stakeholder engagement plan recognizes the diverse information needs of the project's stakeholders. Stakeholder engagement relies on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicts and fostering stakeholder engagement.
Question 8 - ID: 831764
During a project update meeting, one of the key stakeholders expressed his displeasure over the project management approach. One percent of the produced deliverables had minor defects which required a rework. This stakeholder has been a resisting stakeholder so far. What must the project manager do to bring the future project performance in line with the approved quality requirements?
Select one
 
A.
B.
C.
D.
Answer and explanation:
If any stakeholder—resisting or supporting—identifies any issue, it must be addressed. The defects have already been identified and fixed. The scenario is talking about an action that would bring the future project performance in line with the approved quality requirements, this is a corrective action.
Question 9 - ID: 811431
Which of the following is a tool or technique of the Manage Stakeholder Engagement process?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Communication skills is a tool and technique of the manage stakeholder engagement process.
Question 10 - ID: 731804
Jessica is managing an office refurbishment project. All the project stakeholders are identified and classified. The stakeholder engagement plan is also approved. Jessica is managing a project for the first time, and she is relying on the PMBOK guide as a reference to deliver an excellent project. Which of the following processes would provide guidance to Jessica regarding how to execute the approved stakeholder engagement plan?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The question is asking about the stakeholder management process from the executing process group. The manage stakeholder engagement process executes the stakeholder engagement strategy developed during the plan stakeholder engagement process. The monitor stakeholder engagement process deals with making the necessary adjustments to the stakeholder engagement strategy.
Question 11 - ID: 311413
The enterprise environmental factors play an important role during the development of the project stakeholder engagement plan. The following list gives the most significant enterprise environmental factors considered during the Plan Stakeholder Engagement process except one. Which one is it?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Organizational communication requirements should be considered during project stakeholder engagement plan development. However, these are part of organizational process assets and not enterprise environmental factors.
Question 12 - ID: 791261
Which of the following is a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Design for x is a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design. Other choices are either invalid or do not relate to product design.
Question 13 - ID: 621958
Daniel is the project manager for a factory construction project. Daniel has recently joined this organization and is not fully aware of the organization‘s culture and structure. In order to manage his project stakeholders, Daniel has to understand them better. Which of the following can provide Daniel some historical information regarding stakeholder engagement on previous projects?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The project charter and the project management plan do not document lessons learned from previous similar projects. Lessons learned are stored in the organization's process assets library.
Question 14 - ID: 501634
Which of the following tools helps in determining the gaps between the current and desired stakeholder engagement levels?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Monte carlo analysis and the fishbone diagram are risk management and quality management tools respectively. Stakeholder register is a project artifact and not a tool or technique. The correct answer is ‘stakeholder engagement assessment matrix’ which helps a project manager in mapping the current and desired stakeholder engagement levels.
Question 15 - ID: 321266
At which stage in a project should the project manager begin to develop effective stakeholder engagement strategies throughout the project lifecycle?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The project manager starts developing effective stakeholder engagement strategies early during the project’s planning phase. This effort is carried out during the plan stakeholder engagement process and the strategies are then documented in the stakeholder engagement plan.
Question 16 - ID: 671934
Nancy’s project is 80 percent complete. Which of the following project documents is least likely to be updated during the Monitor Stakeholder Engagement process performed at this stage?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The project charter is least likely to get updated during the project execution. Rest of the choices are project documents that do get updated during the monitor stakeholder engagement process.
Question 17 - ID: 441196
Key project stakeholders can significantly influence a project in many ways. During which stage of the project do these stakeholders have the maximum ability to influence a project?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The stakeholder influence is highest at the start of the project and decreases as the project progresses towards completion. This is due to the fact that risk and uncertainty are greatest at the start of the project.
Question 18 - ID: 731070
In projects with adaptive life cycles, many of the project management processes are repeated in each iteration of the project except:
Select one
 
A.
B.
C.
D.
Answer and explanation:
In projects with adaptive life cycles, many of the project management processes are repeated in each iteration of the project except the develop project charter process; which is typically performed only once at the start of the project.
Question 19 - ID: 981209
Linda is currently drafting her project stakeholder management plan. Since she is a new hire, she is not aware of the company’s policies and procedures. If she wants to know more about the company’s general issues management procedures, where must she look?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Linda is looking for company’s policies and procedures. These are part of the organizational process assets.
Question 20 - ID: 831357
A planning package is a work breakdown structure component below the control account and above the work package with known work content but without:
Select one
 
A.
B.
C.
D.
Answer and explanation:
A planning package is a work breakdown structure component below the control account and above the work package with known work content but without detailed schedule activities.
Question 21 - ID: 781030
Increasing the number of resources in order to crash a project schedule does not always cut the time by the same factor. In worst cases, too many resources assigned to an activity may actually increase the activity duration. This is because:
Select one
 
A.
B.
C.
D.
Answer and explanation:
Increasing the number of resources in order to crash a project schedule does not always cut the time by the same factor. In worst cases, too many resources to the activity may actually increase the duration due to required additional coordination. Other choices are either not applicable or do not directly influence the project schedule.
Question 22 - ID: 481474
The stakeholder engagement plan is a subsidiary plan of the project management plan. It includes the strategies required to effectively engage project stakeholders. An ineffective stakeholder engagement strategy can lead to project failure. The stakeholder engagement plan:
Select one
 
A.
B.
C.
D.
Answer and explanation:
According to the pmbok guide, the stakeholder engagement plan can be formal or informal, highly detailed or broadly framed.
Question 23 - ID: 681122
An organization’s value chain can be represented by a special type of flowchart called SIPOC. SIPOC stands for:
Select one
 
A.
B.
C.
D.
Answer and explanation:
SIPOC stands for Suppliers, Inputs, Process, Outputs, and Customers.
Question 24 - ID: 891963
Greg’s project is in the initiating stage. The sponsor of the project has asked Greg to present a list of the identified project stakeholders at the next project update meeting. The sponsor has also asked Greg to present the project stakeholders’ current and desired engagement levels so they can brainstorm on the stakeholder engagement strategy. Which of the following is a presentation tool that can help Greg summarize all this information in a tabular format?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Both the communications and stakeholder management plans are detailed textual documents. They are not presentation tools. On the other hand, both the stakeholder register and the stakeholders engagement assessment matrix contain the required information. However, the stakeholders engagement assessment is the best tool to be selected in this situation since it presents the information required by the project sponsor in a tabular format.
Question 25 - ID: 831367
Sandra is managing a software development project. The project has many stakeholders having a negative attitude toward the project. Sandra knows she can’t keep everybody happy but still can try her best to manage them. Which of the following can help Sandra manage these negative stakeholders better?
Select one
 
A.
B.
C.
D.
Answer and explanation:
Regardless how bad the situation is, send inaccurate project reports is never an option. Further ignoring the negative stakeholders is not recommended. Sending periodic project updates will help but the best way to reduce the negative bias towards the project is to involve the negative stakeholders in project decisions so they get a sense of ownership.
Question 26 - ID: 371960
Christine is managing a healthcare software development project. At a PMI conference, she met George, who is the project manager at a competing organization. George, a PMP, has managed many successful healthcare-related software development projects. If George shares his stakeholder management experience with Christine, will that be considered expert judgment?
Select one
 
A.
B.
C.
D.
Answer and explanation:
George is giving an expert opinion; this is analogous to expert judgment. A PMP-certified project manager from a competitor would not normally give false information. This can be considered expert judgment since george has managed many similar projects.
Question 27 - ID: 651919
During a key stakeholders’ update meeting, George’s project was challenged. The project is currently in the executing phase. One of the key stakeholders claimed the project no longer makes any business sense. What must George do next?
Select one
 
A.
B.
C.
D.
Answer and explanation:
All key stakeholders’ concerns must be addressed. George must first understand these concerns and determine the root cause before taking any action. He must request the objecting stakeholder to provide further details so that he can analyze the situation. Taking immediate action without understanding the problem and determining the root cause is poor project management. Finally, this issue must be recorded in the issue log.
Question 28 - ID: 761914
Andrew is managing a construction project. He is using his communication, interpersonal and management skills to keep the key project stakeholders engaged with the project. Which of the following activities is not related to the Manage Stakeholder Engagement process?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The stakeholder engagement plan is developed during the plan stakeholder engagement process. However, the stakeholder engagement plan might get updated during the manage stakeholder engagement process.
Question 29 - ID: 321579
Which of the following PMBOK processes produces a project stakeholder engagement plan?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The stakeholder engagement plan is produced during the plan stakeholder engagement process.
Question 30 - ID: 801964
Diana is managing the development of a mobile phone application. Half the project work has been completed. Diana is currently reviewing her stakeholder engagement plan. She finds that some of the resisting stakeholders have now become supportive. How should Diana update her stakeholder engagement plan?
Select one
 
A.
B.
C.
D.
Answer and explanation:
The stakeholder engagement plan should be reviewed regularly. Since some of the resistant project stakeholders have now become project supporters, this implies that the current stakeholder classification in the stakeholder engagement plan is no longer accurate. These stakeholders should now be transferred to the project supporters group, and going forward the stakeholder engagement strategy defined for project supporters should be adopted for these stakeholders. Although the stakeholder engagement strategy for the resisting stakeholders has delivered impressive results, it should only be applied to the current resistant stakeholders.